January 2005
To find out how you can help, click here!
January 2005 Update
The locomotive was dismantled and the boiler removed from the frame, the boiler has undergone a survey of metal thickness by ultrasound using a 4" grid pattern over the whole boiler.
Some asbestos found in the boiler dome has been professionally removed and disposed of, Also the boiler has been sent out to be grit blasted.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
This page is prepared and maintained for the Climax Restoration Committee by Frank Stamford and Darren Baker and copyright ©. Last updated on 2 April 2005.
Climax Locomotive No 1694 Restoration Project