Major work is required on the boiler, which is the original one supplied with the locomotive in 1928.
The project will be split into 3 stages as follows
1. Assessment of the boiler, Locomotive Frame and Running Gear
This includes
Dismantling of the Locomotive
Removal of Asbestos from the Boiler Dome
Survey of metal thickness using ultrasound over a 4" grid pattern over the entire boiler
Shear wave testing
Metal analysis to determine exact steel specifications
Grit Blasting of the Boiler
2. Boiler repair and Certification by Chelatchie Boiler Co. USA
This includes
Shipment of boiler from Belgrave to Portland, Oregon USA
Repair of Boiler at Chelatchie Boiler Co.
Manufacture of a new boiler front course
Rivet new front course to the boiler and re tube
Certification and testing to Australian Standards
Return shipment back to Belgrave
3. Repair and Modification to Locomotive and Running Gear
This includes
Manufacture of new smokebox
New castings, such as the blastpipe etc.
Supply, profile and re-tyre wheelsets
None destructive testing of axles for cracking and manufacture if required
Brake system overhaul and modification to suit Westinghouse air brake system
Design and manufacture of spark arrestor and ashpan to appropriate standards
Reassembly of all parts and boiler to Locomotive
Testing, Trials and Accreditation